Project Data
Location
Pilbara Region, Western Australia
Technology
Solar PV, with optional Battery Energy Storage System
Indicative Capacity
Up to 150MWac
Project Status
In Construction
About the project

The Jinbi Project is Yindjibarndi Energy Corporation’s first solar development, located on a greenfield site within Exclusive Native Title land in the Yindjibarndi Native Title Determination Area in Western Australia’s Pilbara region.

The project comprises an initial 75MWac solar photovoltaic (PV) array, with potential expansion to up to 150MWac, and an option to integrate a Battery Energy Storage System (BESS). Jinbi is being developed to provide clean, reliable energy while embedding Indigenous leadership, ownership and long term benefit on Yindjibarndi Country.

In 2023, YEC entered into a Memorandum of Understanding with Rio Tinto to explore collaboration on renewable energy projects. The project reached Financial Close in May 2026, confirming that all key funding, approvals and contractual arrangements are in place. A long term Power Purchase Agreement has been executed with Rio Tinto for 100 per cent of Stage 1 generation. Following Financial Close, construction has commenced, with early site works already underway. Full commercial operations are expected in mid 2028, marking the commencement of the 30 year PPA supply period.

Jinbi EPC Contractor

The engineering and construction of the Jinbi project will be performed on an Engineer, Procurement and Construction (EPC) delivery model. DT Infrastructure has been appointed as the EPC Contractor and will be responsible for all work packages associated with the project's successful delivery. If you are interested in supplier or sub-contracting opportunities with DT Infrastructure,  please contact DT Infrastructure directly.

EPC Contractor
DT Infrastructure
2024–2025
Development
Late 2025
Final Investment Decision (FID)
Early 2026–2028
Construction
Mid 2028
Expected Commercial Operation Date (COD)