Project Data
Location
Pilbara Region, Western Australia
Technology
Wind and Solar PV, supported by battery energy storage
Indicative Capacity
Up to 1GW Wind and 500MW Solar PV
Project Status
In development
About the project

The Eastern Development Zone (EDZ) is a large‑scale renewable energy project led by Yindjibarndi Energy Corporation, comprising up to 1GW of wind generation, 500MW of solar photovoltaic (PV) capacity, and Battery Energy Storage System (BESS) infrastructure.

The EDZ is strategically positioned to support both new and existing energy infrastructure in the Pilbara.

The project is situated approximately 50 kilometres from the proposed Hamersley Range transmission corridor and 80 kilometres from major mining operations, providing strong integration potential with:

  • Future transmission infrastructure
  • Existing industrial energy demand centres
  • Large‑scale renewable energy generation and storage

The EDZ is being developed as a flexible, staged project designed to respond to market demand, infrastructure availability and regulatory approvals, while supporting the long‑term decarbonisation of the Pilbara.

2025–2026
Pre‑feasibility studies, site selection
2026–2029
Feasibility studies, detailed design, stakeholder engagement, preliminary approvals and environmental approvals
2030
Final Investment Decision (FID)
2030–2032
Stage 1 construction
2032+
Commercial Operation Date (COD)